What is Loom: 
Loom is an apparatus/device for making fabric by weaving yarn or thread. It produces fabric by interlacing a series of length wise, parallel yarns width a series of width wise parallel yarns. To get optimum output of loom we must know about the loom production calculation. In this article I have given many examples on loom production calculation.
Loom
Production Calculation of Loom:

Problem-1: 

Production of loom: 

PPM = 200, PPI = 50 

Production per loom per minute =200/50 =4” 

Production per loom per month = 4 x 60 x 24 x 30 inch 

Production per loom per year at 70% efficiency = 4 x 60 x 24 x 30 x 12 x 0.7 inch 
= (4 x 60 x 24 x 30 x 12 x 0.7) / 36 yds 
= (4 x 60 x 24 x 30 x 12 x 0.7) / 39.37 m 
= 36868.68 m (ANS) 

Problem-2: 

PPM = 350 
PPI = 60 
No. of loom = 45 
Time = 7 days 
Efficiency = 90% 

Find out production in m? 

Solution:

                      350                                      90         1 
Production = …….. x (60 x 24 x 7) x 45 x …….. x ……….. m 
                      60                                       100      39.37 

   14288400000 
……………….. m 
     236220 

= 60487.68 m (ANS) 

Problem-3: 

PPM = 650 
PPI = 58 
No. of loom = 10 
Time = 35 days 
Production = 110000 m 

Efficiency = ? 

Solution:

                     650 x 60 x 24 x 35 x 10 x η 
Production = ………………………………….. 
                           58 x 100 x 39.37 

            110000 x 58 x 100 x 39.37 
=> η = ……………………………….. 
             650 x 60 x 24 x 35 x 10 

=> η = 76.77% (ANS) 

Problem-4: 

Find out Wt. of yarn in fabric (warp & weft), from the following specification.

Warp count x Weft count 
.………………………...... x Fabric width 
          EPI x PPI 
or,

20 x 22 
.………… x 56” 
60 x 58 

Solution:

In 5000m fabric, wt of weft warp, 

    60 x 56 x 5000 x 1.05 
……………………………………… kg 
  0.914 x 840 x 20 x 2.2046 

= 521.09 kg (ANS) 

In 5000m fabric, wt of weft, 

   58 x 39.37 x 5000 x 56 x 1.05 
……………………………………… Kg 
     36 x 840 x 22 x 2.2046 

= 457.73 kg (ANS) 

Problem-5: 

Find out the wt. of required warp & weft to produce 5000m fabric from the following specification.

18 x 16 
.………….. x 58” 
66 x 62 

Solution:
 
                            66 x 58 x 5000 x 1.05 x 1.1 
Required warp = ………………………..……...  =  725.28 kg (ANS) 
                            0.9144 x 840 x 18 x 2.0246 

                           62 x 39.37 x 5000 x 58 x 1.05 x 1.1 
Required weft = ………………………...................….. = 766.49 kg (ANS) 
                                36 x 840 x 16 x 2.2046 

Problem-6: 
Calculate the yarn consumption of a loom per hour running at 180 PPM for producing from the following specification.

40 x 60 
…………. x 56” fabric 
72 x 48
 
Solution: 

                                       180               1 
Production/hour/loom ……. X 60 x …… 
                                       48                36 

= 6.25 yd 

                                      72 x 56 x 6.25 x 1.05 x 1.1 
Req. amount of warp = …………………………………
                                            840 x 40 x 2.004 

= 0.393 Kg 

                                     48 x 36 x 6.25 x 56 x 1.05 x 1.1 
Req. amount of weft = ……………………………………
                                          36 x 840 x 60 x 2.024 

= 0.175 Kg (ANS)

Problem-7: 
Calculate the time required to complete a weavers beam having 1000yds of warp on it. The woven cloth is required to have 60 PPI. Loom speed is 200 and efficiency 80%. Assume any missing data. 

Solution:

                                       210      60 
Production/loom/hour = ……. x ….. x 0.8 
                                       60        36 

= 4.67yds 

                   Length of cloth from the beam 
Time req. = ………………………………… 
                       Actual production/hr 

Length of cloth from the beam, 

                                      100 – crimp 
= (Length in yds of warp x …………….) – Waste in yards 
                                           100 

               100 – 6 
= (1000 x …………) – 6 
                 100 

= 934 yds 

                                 934 
So, Time required = ………. 
                                 4.67 

= 200hr (ANS) 

Problem-8: 
Calculate the actual yarn consumption per month of weaving mil having 100 looms of 250 ppm for the following fabric construction. Considering each point. 

80 x 60 
…………. X 56” 
110 x 54 

Production per month of 100 looms at 100% efficiency, 

   250                                100 
…….. x (60 x 24 x 30) x ……. 
    54                                  36 

= 555556 yds 

                                           110 x 56 x 555556 x 1.05 x 1.1 
Required amount of warp = ………………………………… 
                                                     840 x 80 x 2.204 

= 26687 Kg 

                                            54 x 36 x 555556 x 56 x 1.05 x 1.1 
Required amount of weft = …………….....……………...…….. 
                                                     36 x 840 x 60 x 2.204 

= 17468 Kg (ANS)

Problem-9: 
Find out thrust in Newton to drive a loom by using plate clutch system and conical clutch system. If F=425N, μ=0.45 and θ=20° 

Solution:

                                   F           425 
For plate clutch, P = …….. = ………. = 944.44 Newton 
                                  µ            0.45 

                                                 F sin θ     425 sin 200 
For conical clutch system, P = ………. = …………… = 323.02 Newton (ANS)
                                                    µ               0.45 

Problem-10: 
Calculate the production per shift of 10 hrs at 90% efficiency a weaving mill in average 22 picks per cm from the following information: 

No. of looms .........picks/cm .........PPM 
120 ........................20 ...................220 
16 ..........................25 ....................210 
110 ....................... 28 ................... 200 

                                              220                       90                1 
Production at 22 picks/cm = …… x (60 x 10) x …….. x 120 x ……. 
                                               20                       100              100 

= 6480 m 

                                             220                      90             1 
Production at 22 picks/cm = …… x (60 x 10) x ….. x 16 x ……. 
                                              20                      100           100 

= 824.73 m 

                                            220                      90               1 
Production at 22 picks/cm = …… x (60 x 10) x ….. x 110 x ……. 
                                             20                      100             100 

= 5400 m 

Average production = (6480 + 824.734+5400) m 

= 12704.73 m (ANS)

Problem-11: 

Calculate the “speed space” required to produce a elastic fabric having 30% shrinkage (width of finished fabric 50″) 
                                                    130 
Required reed space = 11 x 50 x …… 
                                                    100 

= 65 inch (ANS)